Product Description: Headphone Power Test Equipment Cable Fault Pinpointer locator with accuracy <0.1M
1.Introduction:
PCLD-904P Digital Power Cable Fault Pin-pointer is an easy operation device used to pinpoint the fault point. It integrated the function of acoustic magnetic synchronization method, the step voltage method, the magnetic field strength method to make the pinpointing accuracy.
NO | NAME | INTRODUCTION |
1 | LCD | |
2 | KNOB | Adjust the acoustic gain or cursor; Adjust the magnetic gain Setting the interface |
3 | SET/POWER | Long time press: power on/off;short time press: enter or exit |
4 | MUTE | Headphone on/off |
5 | CURSE/GAIN | Adjust cursor or gain |
6 | BREATHER VALVE | |
7 | SIGNAL INPUT | Use the signal line to connect with the sensor |
8 | STRAP HOOK | Install the strap |
9 | HEADPHONE INPUT | Connect with the headphone |
10 | CHARGING PORT |
NO | NAME | INTRODUCTION |
1 | Pole | Install method: insert into the open hole and rotate the pole as one quarter turn |
2 | Long probe | Used for the lawn or soft ground. Remove it and install in the screw hole in the bottom |
3 | Signal port | Use to contact with the main unit with signal line |
4 | Breather valve |
2).Terms of Shipment:
Within 10 working days after received related prepayment or L/C.
3).Payment terms:
(1)T/T 100% or 50% deposit by T/T in advance, balance amount to be paid 7 days before
delivery.
(2) By irrevocable L/C at sight, to be issued immediately against confirmed order.
(3)Payment by T/T, if order amount is less than USD 20,000.
4).Warranty:
(1)We provide 1 year warranty.
(2)If the product is defective, please notify us within 3 days of delivery.
(3)All products must be returned on their original condition, in order to qualify for a refund or exchange of goods
5.Flow chart of trading activities:
NO | Step | Days need |
1 | Request for quotation | 1 day |
2 | Making quotations | 1 day |
3 | Offer and counter offer | 3 days |
4 | Sending and receiving samples | 3-10 days |
5 | Sample confirmation | 3 days |
6 | Placing a firm order | 1 day |
7 | Paying and receiving the down payment | 1-4 day |
8 | Factory production & Quality inspection | 15-20 days |
9 | Paying and receiving the balance | 4 days |
10 | Delivery of goods | 1 days |
8.Contact
Products with this tag will be sent out within 15 days after you place an order. For the specific sending time and delivery date, please consult the supplier.
*If the supplier with the above tags do not give you the according discount or service, you can click "Contact Us" to make a complaint. If what you said is true, our professional team will help you to handle this problem.
If you are using our website on PC, you can find us by this way:
Go down to the bottom of Made-in-China.com > Go to "Help" Section> Contact Us
If you are using our Made-in-China.com App, you can find us by this way:
My Account > Click setting section which is in the top right corner > Contact Us